Contracting

Project NameScope of Work DetailsClientEnd UserYear
3 Years Annual maintenance Contract of Siemens/ABB Drives & Siemens PLC 3 Years Preventive maintenance, emergency visits & remote support Covering Siemens/ABB MV & LV drives & PLC Siemens for line # 4 & Lin # 5 & Power plantYCC | Yanbu Cement CompanyYCC | Yanbu Cement Company2022
Installation of (mechanical /electrical ) and commissioning assistance of cooler line 1 cooling fans'Drives, Motors and cablesInstallation of (mechanical /electrical ) and
commissioning assistance of cooler line 1 cooling fans'
Drives, Motors and cables
Eastern CementEastern Cement2022
SUBSTATIONS S87 & S88Installation of PLC/RTU, server, switch panels, cables, cable trays, fiber optic cables, Ethernet and MODBUS Cables, IED switches inside MV switchgears, Termination of signals between PLC’s/RTU’s and field equipment – Switchgears, Transformers and etc in Haram Mecca with Ben ladin.ABBSBG2022
Project BEMCO - MFRR SCADA (Haram Mecca)Installation of PLC/RTU, server, switch panels, cables, cable trays, fiber optic cables, Ethernet and MODBUS Cables, Termination of signals between PLC’s/RTU’s and field equipment – Switchgears, Transformers and etc In Haram Mecca with BEMCO.ABBBEMCO2022
Annual Maintenance Contract for Ref-PACK & Defrost UnitsAnnual Maintenance Contract for PLC/HMI/SCADA/VFD Systems
Siemens & Mistsubishi brand
Rockwell AutomationMakkah Plant2022
Electrical Technicians Manpower Electrical Technicians Manpower Rockwell Automation2022
Instrument Technician for Tasnee ProjectInstrument Technician for Tasnee ProjectRockwell Automation2022
Modification for LV MCC PanelTesting for ACB & Busbars, Testing of three Motors DOL Starters Rockwell AutomationP&G Factory2022
Supply and laying LV cablesSupply & laying LV cables Advanced Fabrics Factory Company Advanced Fabrics Factory Company2021
Supply and install power panelsSupply and install power panels Advanced Fabrics Factory Company Advanced Fabrics Factory Company2021
Cables laying and terminationCables laying and termination including cable tray Advanced Fabrics Factory Company Advanced Fabrics Factory Company2021
Supply & laying LV cables and rehabilitation of the existing panelsSupply & laying LV cables and rehabilitation of the existing panels Advanced Fabrics Factory Company Advanced Fabrics Factory Company2021
Supply & install of Water Quenching Piping CFT Supply & install of Water Quenching Piping CFT including all electrical and mechanical worksAl Safwa Cement CompanyAl Safwa Cement Company2021
Supply & install LV cablesSupply & install LV cables including excavation work & laying cablesSaudi Cement CompanySaudi Cement Company2021
Replacement of L#2 Generators Power & Control Panels Replacement of L#2 Generators Power & Control panels including additional cubical for solar incomer panel solar system with all cable and installation work associatedSCMC | Southern Cans Manuf.SCMC | Southern Cans Manuf.2021
Electrical Contracting works for solar systemSolar electrical contracting and panels supply for solar projectDesert Technologies Co.SCMC | Southern Cans Manuf.2021
Removing the damaged cablesRemoving the damaged cables Advanced Fabrics Factory Company Advanced Fabrics Factory Company2021
Supply & Install Panels, LV Cables & Cable traysSupply & Install Panels, LV Cables & Cable traysMawared Al-Hayat Water CompanyMawared Al-Hayat Water Company2021
Site Installation WorkSite Installation WorkRockwell Automation NWC2021
Site Installation WorkSite support and installation including installation accessoriesRockwell Automation ALBA SPL2021
Site Installation WorkSite Installation Work for NWC Saad Pumping Station PKG2Rockwell Automation NWC2021
MV cable laying including jointsMV cable laying including jointsSaudi Cement CompanySaudi Cement Company2021
Supply & install of LV panels at Admin building Supply & install of LV panelsSaudi Plastics Products CompanySaudi Plastics Products Company2021
Supply & Install Main Bords, LV Cables & Cable traysSupply & Install Main Bords, LV Cables & Cable traysBAJA FOOD INDUSTRIESBAJA FOOD INDUSTRIES2020
Supply & Installation of 36KV MV Termination Kit, MV Cable DC Hipot testingSupply & Installation of 36KV MV Termination Kit, MV Cable DC Hipot testingNATPET | National Petrochemical Industrial CoNATPET | National Petrochemical Industrial Co2020
Supply of ethernet cables, SiemensSupply of industrial ethernet cables, SiemensSaudi White Cement CompanySaudi White Cement Company2020
Supply & Erection of Cables & Cable TraysSupply & Erection of Cables & Cable Trays in Al-Ayoun FactorySaudi Plastic Packaging SystemSaudi Plastic Packaging System2019
MCC Feeder Upgrade E&I WorkMCC Feeder Upgrade E&I WorkUSC | United Sugar Company / SAVOLA GroupUSC | United Sugar Company / SAVOLA Group2019
E&I CONSTRUCTION WORK FOR ONE MASS FLOWMETERE&I CONSTRUCTION WORK FOR ONE MASS FLOWMETERUSC | United Sugar Company / SAVOLA GroupUSC | United Sugar Company / SAVOLA Group2019
Supply and install MV END TERMINATIONSSupply and install MV END TERMINATIONSQCC | Qassim Cement Company QCC | Qassim Cement Company 2019
Site Installation WorkSite Installation WorkRockwell Automation NOMAC2020
Installation of meters and CTsInstallation of meters and CTsRockwell Automation PepsiCo2019
Supply & Installation of Fiber Patch Cords & Checking Fiber Connection to 9 RTU'sSupply & Installation of Fiber Patch Cords & Checking Fiber Connection to 9 RTU'sABBMOI / Security Forces Hospital2019
Panels installation & Cable laying, Maaden Barrick Copper CompanyPanels installation & Cable laying, Maaden Barrick Copper CompanyRockwell Automation Maaden2019
Installation & cable termination of Disconnect switches
Included Cable Gland & Cable Lugs, Raychem Sleeve
Installation & cable termination of Disconnect switches
Included Cable Gland & Cable Lugs, Raychem Sleeve
Rockwell Automation PepsiCo2019
Panels installation & Cable laying, Aramco GCCPanels installation & Cable laying, Aramco GCCRockwell Automation ARAMCO2019
Supply & Installation of LV Accessories panel, PepsiCoSupply & Installation of LV Accessories panel, PepsiCoRockwell Automation PepsiCo2019
Site support and Installation works, NOMACSite support and Installation works, NOMACRockwell Automation NOMAC2019
SUPPLY AND INSTALL THE ELECTRCIAL WORK FOR THE THE CHILLED WATER CENTRALIZATION PUMPS MCC PANELSUPPLY AND INSTALL THE ELECTRCIAL WORK FOR THE THE CHILLED WATER CENTRALIZATION PUMPS MCC PANELAFIA / SAVOLAAFIA / SAVOLA2018
Shifting of factory electrical and automation equiments to the new location including commissioning and start upShifting of factory electrical and automation equiments to the new location including commissioning and start upJewel Tech ContractingAl-Khayyat plastic strapping factory2018
Supply & install of Lighting productsSupply & install set of High mast 25M
with all Accessories and Lighting fixtures
CCC | City Cement CompanyCCC | City Cement Company2018
Supply of SparesSupply of Luminarie –Halogen FloodlightQCC | Qassim Cement Company QCC | Qassim Cement Company 2018
Supply and install the Electrical source connection to new HUSKYSupply and install the Electrical source connection to new HUSKYAFIA / SAVOLAAFIA / SAVOLA2017
Electrical works of the Royal Commission project No.531/37Supply & Install of the electrical works of the Royal Commission project No.531/37Electrical World CompanyRoyal Commission in Jubail 2017
Design, Supply, Installation & Commissioning of Building Management System (BMS) including all cabling and sensors work for Radisson Park Inn hotel / JeddahDesign, Supply, Installation & Commissioning of Building Management System (BMS) including all cabling and sensors work for Radisson Park Inn hotel / JeddahSaad Al-Harthy GroupRadisson Park Inn Hotel2016
LAC TANKS Fire Alarm SystemDesign, Supply, Installation & Commissioning of LAC TANKS Fire Alarm System including all cabling and instruments workUSC | United Sugar Company / SAVOLA GroupUSC | United Sugar Company / SAVOLA Group2016
Light Current SystemsSupply & install fire alarm ,CCTV,DATA ,satellite, central watch SystemsAl-Aham for civil and construction works CompanyTADAWI Hospital2016
Turnkey complete Electrification Erection work for the new factory including all light current systemsTurnkey complete Electrification Erection work for the new factory including all light current systemsElectrical World CompanyRiyadh Carton Factory / Riyadh2014
Turnkey project for the new factory including all light current systemsElectrification Erection work for watnia factory for red bricks in DormaElectrical World CompanyWatania Red Bricks Factory2014